Demolition Schedule / Updated: March 17

Cornerstone Construction Company is working on removing some of the concrete floors in all six of the theaters. The outside wall of one of the theaters will be taken down on Thursday so they can begin filling and leveling the floors in all of the theaters next week. I will let you know how you can help but for now we are on hold.

We can continue to strip the insulation off the copper wires that we have removed from the building. I will be at the theater Wednesday 3/18 and Thursday 3/19 from 4-8 PM if you would like to come and help with this process. We currently have 4 razor blade knives available. Please bring your own razor blade knife if you have one. I will supply the razor blades for the knives. You can also stop by the theater during that time and pick up some wire and strip it at home! You can bring it back to the theater anytime that we are scheduled to work in the future and we will add it to the collection.